This Week
While work was initially anticipated to return to the culvert area, crews instead began work on the duct bank at the Depot Street end of the project area while coordinating schedules with the concrete crew. Upcoming work near the culverts will include installation of headwalls, handrails, and erosion control measures.

Please expect intermittent road closures along Howard Street and in the adjacent alleyway to accommodate construction activity.

Progress from the Past Week

  • Crews successfully completed the replacement of all three culverts.

Thank you for your ongoing support as we continue working toward a safer, more beautiful, and pedestrian-friendly Howard Street!t!