After the holiday break, crews are back at it and have resumed work on stormwater installation. Work will begin in front of the gravel lot adjacent to the green building located at 274 Howard Street and will continue moving toward Depot Street.

As always, thank you for your patience as we keep things moving forward. Please reach out if you have any questions.