Last Week
Crews made solid progress by completing the final two water service connections to the new line and installing the last section of stormwater line. These were two important milestones as the project continues moving toward the final phase of underground construction.

This Week
Looking ahead, work plans for this week are still being finalized as crews work through a few remaining updates related to duct bank installation. If those details are completed as expected, duct bank installation is anticipated to begin in the area next to Footsloggers.

If duct bank items require additional coordination time, crews will shift to surface-level grading around the stormwater boxes so that progress can continue while those final duct bank details are wrapped up.