If this week’s update feels a little familiar… you’re not wrong. Work is continuing in the same general area, and steady progress is being made along the corridor.
Last Week
Crews completed approximately 10 utility box installations of varying sizes (some of them rather large) between Depot Street and Burrell Street. These boxes are part of the underground duct bank system and will house and protect electrical and communication connections.
This Week
Crews will continue working between Depot Street and Burrell Street to install additional utility boxes for the conduit system (those gray pipes you currently see extending from the ground).
Please note that the contractor has a work event planned later next week. If crews are onsite Wednesday through Friday, staffing levels may be lighter than usual during that time.
As always, thank you for your continued patience as this work moves forward. If you have any questions, don’t hesitate to reach out 828-268-6283.