This Week:
Howard Street is looking a little greener! With the bulk of the landscaping installed over the weekend, crews may be back in the area this week for touch-ups and finishing work.
Charter/Spectrum’s subcontractor is also continuing work to move utilities underground. So far, impacts have largely been limited to the temporary use of a few parking spaces to access the underground duct bank.
Last Week:
Crews focused on preparing for landscaping, followed by installation of most of the plants over the weekend. It’s exciting to see this finishing touch take shape, with a little more work expected this week! Charter/Spectrum also began its portion of the underground utility work, marking another step toward project completion.
If you have questions, please call at 828-268-6283.